InterPlan Systems News


eTaskMaker Module Updates for December / January

InterPlan Systems has released the following updated eTaskMaker estimating modules:

  • Agitators (Rev.3)(updated) Estimating formulas have been updated and improved.
  • Asbestos Abatement (Rev.5)(updated) Added a factor for hazardous environmental conditions.
  • Blowers (Rev.3)(updated) Added a factor for hazardous environmental conditions.
  • Channel Head Belzona Repairs(new) Simple template module.
  • Drums (Rev.9)(updated) Major revision incorporates more scenarios and parameters for tighter estimates.
  • Electrical Conduit Re-routing(new) Simple template for re-routing conduit at a pump.
  • Electric Motors Starters & Push Buttons (Rev.1)(updated) Added a factor for hazardous environmental conditions.
  • Flare – Shop Repair(new)
  • Floating Head Repairs(new)
  • Heat Exchangers – Fixed Tubesheet (Rev.5)(updated) Additions including burning off severely corroded bolts and eddy current testing.
  • Heat Exchangers – Floating Head (Rev.6)(updated) Additions including burning off severely corroded bolts and eddy current testing.
  • Heat Exchangers – U-Tube (Rev.9)(updated) Additions including burning off severely corroded bolts and eddy current testing.
  • Heat Exchangers – Vertical (Rev.6)(updated) Additions including burning off severely corroded bolts, eddy current testing and improved definition of tasks for refacing damaged flange surfaces.
  • Level Transmitters – Field Service(new)
  • Pipe Insulation – Calcium Silicate(new) Allows for insulating either rack or off-rack piping, from pipe diameters 4 through 12 inches and insulation thicknesses up to 4 in.
  • Pipe – Field Erection (Rev.5)(updated) Major revision allows you to specify either on-rack or off-rack erection, and improved insulation task definition.
  • Pipe – Small Bore (Threaded) Field Erection (Rev.2)(updated) Added steps for mobilization and installation of metal jacketing on insulation.
  • Piping Demolition (Above Ground) (Rev.2)(updated) Major revision includes improved scaffolding definition and improved estimating formulas.
  • Piping Demolition (Under Ground) (Rev.3)(updated) Major revision includes tasks for breaking up concrete and repairing or leaving the trench open for further work, enhanced estimating formulas, and permitting tasks.
  • Primary Reformer Tubes Pigging(new)
  • Pumps (Rev.3)(updated) Includes tasks for the removal and re-installation of insulation and steam tracing and the coupling guard.
  • Push Buttons(new)
  • Repair Damaged Gasket Surface on Manway(new)
  • Retube Floating Head Tube Bundle(new) This is for retubing a bundle with two tubesheets and straight tubes (as opposed to a U-tube bundle, that has only one tube sheet,and tubes must be bent).
  • Safety Valves (PSVs) (Rev.3)(updated) Allows for blinding a nozzle on a vessel after removal of the PSV.
  • Salt Dryer(new)
  • Sparger Replacement (Rev.1)(updated) Added a factor for hazardous environmental conditions.
  • Towers (Rev.10)(updated) Major update includes:
    • Added scope for environmental hazard conditions requiring extreme safety procedures
    • Improved estimating formulas
    • Updated resource assignments
    • Added a sequence for opening unsupported manways (with crane)
    • Added a multiplier for multiple packing beds (pall/raschig rings)
    • Added tasks to remove, clean, inspect and replace tower bottom spool
    • Added tasks to remove, clean, inspect and replace the vortex breaker
    • Included tasks for cleaning the tower bottom depending on the degree of fouling

eTaskMaker clients may now download the updates from our downloads repository.

New ATC enhancements available

A new update for ATC Professional is now available from the the client download repository that includes new functions for analyzing progress with respect to the baseline schedule. The update also includes a couple of new options for formatting the Bar Chart report.

We have several more enhancements in development that should be released within the next few weeks. Contact us for more details.

Free eTaskMaker and ATC Professional Seminar Set for December 8th

Our most recent seminar was well received by attendees from Total Petrochemicals, Bay Ltd., Air Products and Chemicals, Rohm and Haas and Mundy.

The next scheduled free eTaskMaker seminar is set for Thursday, December 8th. The seminar will show how to use the eTaskMaker Wizard and ATC Professional demo to produce cost reports for preparing AFE budget estimates.

It will be held at the Houston Business Roundtable’s training facility across from Houston’s Hobby Airport. Attendance is free, but pre-registration is required to guarantee a seat. Sign up today! We hope to see you there.

eTaskMaker Module Updates for October

InterPlan Systems has released the following updated eTaskMaker estimating modules:

  • Air Cooler Erection (Rev.1)(updated) Estimating formulas have been updated and improved.
  • Block Valves – Bolted (Rev.7)(updated) Included option to exclude equipment demobiliztion.
  • Blowers (Rev.2)(updated) Improved PDM schedule logic.
  • Blind Installation (Rev.2)(updated) Included option to exclude equipment demobiliztion.
  • Foundation – Concrete (Rev.7)(updated) Major revision incorporates tasks for building a concrete foundation with pedestal (either steel or concrete) with saddle for a drum.
  • Vessel Erection (Rev.4)(updated) Major revision incorporates improved estimating formulas and additional tasks for removal of trunnions, temporary internal bracing, testing of spray patterns.
  • Pipe – Field Erection (Rev.3)(updated) Updated resources assigned to blind installation tasks.

eTaskMaker clients may now download the updates from our downloads repository.

*NEW* – eTaskMaker Lite

InterPlan Systems now offers a more affordable version of their eTaskMaker project planning software for clients outside of the refining and petrochemical industries. Dubbed eTaskMaker Lite, this new version offers more attractive licensing terms for clients who do not need access to the planning library for process plant maintenance that is bundled with the eTaskMaker standard version.

While eTaskMaker Lite is fully functional (with the exception of being able to utilize InterPlan’s library of “public” modules), there are a few important differences in the licensing terms versus eTaskMaker standard. Please refer to the eTaskMaker Lite page for more details.

eTaskMaker Module Updates for September

InterPlan Systems has released the following updated eTaskMaker estimating modules:

  • Sump Pump Installation (Rev.1)(updated) Estimating formulas have been updated and improved.
  • Compressor Motor (Rev.1)(updated) Improved estimating formula based on motor size (in HP).
  • Blind Installation (Rev.1)(updated) Improved PDM schedule logic.
  • Drums (Rev.7)(updated) PDM schedule logic was updated. Estimating formula for crew size on blind removal was updated.
  • Fugitive Emissions Identification (Pre Turnaround)(new) For capturing the effort in tagging leaks pre-turnaround.

eTaskMaker clients may now download the updates from our downloads repository.